Earth Force Technologies, Inc. - EF Build

Operating Plan - First 6 Months

Vision Ridge Partners · $250M investment

October 2026 – March 2027

Public to read. Invited editors keep the plan, the people, and the work product — files, tests, drawings, offtake, supply — on one record as they change.

Spend is in the controlling 6-month budget document. This is the operating plan that budget funds.

Last saved 8/30/2026, 2:04:27 AM

01

Purpose

This is the operating plan for EF Build from October 2026 through March 2027.

It sets destination, Strategic Intents, places, products, owners, and 30 / 60 / 90 / 180-day actions.

This window locks a replicable, certifiable component-and-cell foundation that later factories copy. It does not stand up five production lines.

Stewart, Beyreuther, and Staneff do the work only they can do. Hires are doers that extend them, not managers beside them.

Long-lead equipment is an 18-month timer. POs in October start that clock.

02

Destination

Earth Force Build starts at forest stewardship and wildfire mitigation, controls source fiber, and converts it at the lowest transformational energy and cost at each stage into high-precision components and assemblies. That conversion system is the Platform. The Platform is how products are developed.

Products are configured from one characterized, certifiable component set, inside certified and manufacturable limits. They do not extend the set. A part that is not in the set does not go to production start.

Design rule: precision CLT / thin CLT and subtractive process. Eliminate unnecessary parts, pieces, spacers, adapters, connectors, and frames. Highest performance through more elegant design and material; lowest transformation cost - measured in energy, labor, currency.

A process cell is not a hero setup in Factory 0. A cell is specified so a production team can run it: equipment, utilities, quality limits, labor, first-article criteria, and ledger points. Factory 1 and later factories execute with developed process cells. They do not reinvent them through operations.

Mature production: process cells optimized for each component; components into sub-assemblies; sub-assemblies assembled at in-market facilities; final assembly on site. In-market assembly facilities follow Factory 1 at production speed, when offtake warrants those facilities.

Deployment speed does not equal risk. Here it is the opposite.

A linear path - characterize, certify, tool, product, then customer, and repeat - reaches mature production in 20+ years. Running characterization, certification, cell development, product engineering, customer conversion, and finance in parallel puts mature production on a 3-year track. This plan is the parallel path.

Linear / in seriesThis plan
CertificationCloses before toolingUnderway now, with cells and products
CapacityAfter certified productFactory 0 cells now; Factory 1 as build-to-suit
ProductsOne, then the nextAll example products configure the same set, in design and engineering now
CustomersAfter the line existsLOIs advanced against SI 1 evidence and SI 2 packages
FinanceAfter production existsOfftake and working-capital structure starts now
Component setCustom parts per projectOne certified set; products configure it
PartsAdapters, spacers, extra connectorsSubtractive precision; eliminate what is not required
System of recordAfter the line existsLedger from first coupon and first cell
CellsA line that works in one buildingSpecified to be copied to Factory 1 and production teams
Mature production20+ years3-year destination
03

Demand

The United States is a ~$1.3T construction and development industry. Housing shortfall and industrial demand for schedule, carbon, and repeatable assemblies are already measured and well documented. Offtake waits on certified, manufacturable capacity a large developer can underwrite. Evidence is found in the Earth Force Build detailed, conservative, and variable market diffusion models for the 4 PNW states, expanding to the rest of our coverage area.

The first prototypes and pilots are for qualified launch partners, where each is contributing components to the platform that serves greater demand than modeled. Starting at cost parity in each of their respective product categories, the demand is represented by the markets, not individual projects.

  • Certification — characterized Platform and documented build system that an AHJ, insurer, lender, and offtake counterparty can stand behind.
  • Capacity — process cells that release conforming product, specified so they can be copied, and a production system that takes those cells at speed.
  • System of record — every coupon, cell cycle, and first article writes to the ledger. Scale without that is tribal knowledge.

Market development and structured finance for Build offtake start in this window, led by Justin Stewart. Ownership of BU P&L, institutional counterparties, external development projects, and overall strategy. CFO hired in months 0–6, with Build functions reporting to Stewart, to take strategic structures, facilities, and reporting.

04

Products

One Platform. One characterized, certifiable component set. Five example products configure that set — they do not extend it. Shared cells and modules are the work; product SKUs are the configurations.

A prototype remains under Earth Force control. A pilot is permitted and delivered on a customer site.

Schweitzer Mountain (executed LOI)

Customizable SFH - Avalanche

Permitted and delivered on site

Teaches configurable SFH inside the certified set. Design and engineering start now. Production start in 6 months only for parts in the set.

Schweitzer Mountain (executed LOI)

Townhomes

Permitted and delivered on site

Same set as Avalanche. Schweitzer site pilot. Design and engineering start now. Production start in 6 months only for parts in the set.

Unbrick USA (500+ units/year path)

Product SFD

Permitted and delivered on site

Offtake volume path. Same cells as Schweitzer. Design and engineering start now. Production start in 6 months only for parts in the set.

Cloud Apartments; Cypress Equity and LH Housing initial offtakes, 1000+ units/year offtake path

Stacked flats

Four prototype units built and stacked 2x2 in Factory 0

High volume stacked-unit offtake path. Four Factory 0 prototypes this period prove the set in stack. Site production later.

Knife River Precast, Newman Lake, WA

Industrial building system

Test panels, then assemblies, then demonstration product on our site

Factory 1 building system with Knife River. Test panels, then assemblies, then demonstration on our site. Teaches industrial cells. No production-start date this period.

Modules

Wet-room, bathroom, and kitchen modules are Platform components, they are not product SKUs. They are used across Unbrick, Schweitzer, Cloud factory prototypes, and industrial as required. They are built from process cells for each part, specified to be copied. Resia Manufacturing commissioned equipment is acquired Day 1. Prototypes and pilots run mostly on 0.0 cells; 0.1 as bathroom production cells come online. A module cell is done when it meets the set, writes to the ledger, and has no unnecessary parts.

Cloud Connect

Cloud Connect is factory-installed vertical plumbing waste, drain, vent, and water, with on-site vertical quick-connects during setting. It is specified first on Cloud Apartments and may be used on other stacked-unit product.

05

Places

  1. 01

    Factory 0 — 11016 E Montgomery Dr, Spokane Valley

    77,000 sq ft, former Katerra Factory 0. Process-cell development and iteration, not a production line. First articles. Four Cloud prototypes. Cells specified here so they can be released to production teams and copied into Factory 1. Every cell cycle writes to the ledger.

  2. 02

    Knife River — Newman Lake, WA

    Industrial panels and assemblies.

  3. 03

    WSU and specialty labs

    Testing until the Earth Force lab is operational. Lab planning and design start now. The EF Lab is not operational in this window.

  4. 04

    Factory 1 — first purpose-built production factory

    In site selection. ATI, Leavitt Capital, and Aaron Lake are planning a build-to-suit using the Earth Force / Knife River industrial building system. Planning, not closed.

Immediate supply: IFG (domestic fiber), Mercer International (CLT panels), KLH (international CLT panels and components). Import is a bridge and risk reducing redundancy while U.S. characterization, certification, and conversion come online. SI 1 test matrix includes incoming mill variance across IFG, Mercer, and KLH so the certified set is not mill-specific. Source-fiber control through stewardship is the mature-state supply position.

06

Strategic Intents

SI 1, SI 2, and SI 3 run concurrently. SI 1 leads; SI 2 uses SI 1 output; SI 3 stands up Factory 0 cells against both.

SI 1

Characterized and certifiable platform

Future state

Validated technical basis for products and processes; certification underway; major technical risks defined; component-set rules that later factories copy without reinventing characterization.

Now

Material, product, and process characterization, including incoming mill variance (IFG, Mercer, KLH); prototypes, testing, and approved-agency engagement; certification strategy, reports, and quality-system development; laboratory and technical-partner POs. Every coupon and assembly writes to the ledger. Agency list, listings, and order of operations follow Beyreuther’s certification package (code reports, product / process / environmental certs, chain of custody, QA/QC, factory certification).

SI 2

Designed and documented build system

Future state

Building products designed and documented to support pricing, customer evaluation, permitting, and credible offtake — all as configurations of one set, not as five independent systems.

Now

The shared-component list is the primary artifact. Products are configurations of that list. Architectural and engineering product design inside certified and manufacturable limits; design-to-cost, scope, schedule, and performance documentation; conversion from interest to project-specific offtake. No product-specific part outside the set proceeds to production start. Eliminate unnecessary parts at the design.

SI 3

Designed and documented production system

Future state

Production processes, equipment packages, and site interfaces ready for final capex authorization and deployment.

Now

Process flow, equipment, layout, and utility engineering for cells that can be copied; supplier design scopes, lead times, and manufacturing slots; engineering deposits and selected down payments; Factory 1 site selection and alternative site scenarios. A cell package includes equipment, utilities, quality limits, labor, first-article criteria, and ledger points. Beyreuther is the architect. Head of Industrialization owns cell packages when seated, reporting to Beyreuther. Stewart holds P&L, capex authorization, and Factory 1 commercial path.

07

Organization

Head of Build

Justin Stewart

Full P&L for the EF Build business unit. Directly over market and offtake development, strategic finance for Build offtake, external development projects (Earth Force’s offtake partners), and overall strategy. Supplier and customer POs/WO's, Factory 1 incentives and build-to-suit, staffing. Strategic Projects Senior Associate reports here — IB/PE doer across finance, operations, and product. Build CFO function reports here. Factory 0 occupy and commercial control until operations exist beyond proto and cells.

Head of Platform

Todd Beyreuther, PE

Owner and architect of the system. The engineer who enables the entire system to work together: certified component set, configurable boundaries, characterization, certification strategy, process / safety / quality by design. Product engineer and product architect are doers under this seat. Head of Industrialization reports here to begin with.

Head of Ledger

Geoff Staneff, PhD

One ledger: forest floor through transformation into flitches, lamstock, CLT, components, assemblies, finished buildings, and on through performance, maintenance, and reconfiguration decades out. Scientific innovation and development of technical innovations: materials science applied to the Platform, not a side lab. Jennifer Steinhardt (Digital Backbone) is the doer under this seat. Ledger is live from first coupon and first cell — not a document exercise after the fact.

Industrialization

To hire - Day 1 search. Reports to Beyreuther to begin with.

Director of Process Development immediately. Acting Manufacturing Operations through proto and cell development, learning and building the systems of record on live work. Cell packages specified to be copied. Not a second executive layer. A specialist Manufacturing Operations hire comes later, when there is manufacturing operations beyond proto and cells.

CFO

To hire, months 0–6.

Takes capital structure, offtake-finance facilities, working capital, draws, and reporting off Stewart. Search starts Day 1. In seat by Day 180. Stewart keeps institutional counterparties and strategic finance for Build offtake until then.

Day 1 doers: product engineer and product architect offers under Beyreuther; Head of Industrialization search (reports to Beyreuther to begin with; Process Development now; acting Manufacturing Operations through proto and cells); process engineer; Factory 0 HSE; codes/certifications capacity under Beyreuther; Strategic Projects Senior Associate under Stewart (IB/PE; finance, operations, and product); CFO search (Build functions report to Stewart). Day 60–90 doers: factory PM; permit PE/architect; controls; Controller (reports to Stewart until CFO sits); small Factory 0 crew. Day 180: Site Operations; founding Factory 0 production seats; CFO in seat. Not this period: Director of Product Development, Director of Policy Development, Director of Content Development, specialist Director of Manufacturing Operations, offtake PM layer, full factory benches.

08

Hiring sequence

Hire to the work clock, not to the mature org chart. The attached org/role chart is the destination. This sequence is who must be engaged so SI 1, SI 2, and SI 3 can run in parallel, and so physical prototype and pilot work starts on time.

Stewart, Beyreuther, and Staneff are the constraint and the advantage. Stewart: P&L, offtake, strategic finance, external development, strategy. Beyreuther: overall owner and architect of the Platform; the engineer who makes the system work together. Has design authority on all components, assemblies and process cells. Staneff: one ledger from forest floor through decades of building performance; scientific innovation and development of technical innovations. Hire doers that extend them. Stewart’s Strategic Projects Senior Associate is the doer across finance, operations, and product, from analysis through execution. Do not hire directors of Product, Policy, or Content this period. Do not hire a Manufacturing Operations specialist. Industry-changing scale is a certified set, copyable cells, and a live ledger, not an org chart filled early.

SI 1 (characterize / certify), SI 2 (design / document the build system), and SI 3 (design / document the production system) start together. Design and lab work have no floor lag. Factory 0 cell development, Resia Day 1, and first articles do. People who do that work must already be engaged when the work starts.

Named contractors and lab partners start faster than FTE. FTE searches open Day 1 with a 60–90 day time-to-seat. Product engineer and product architect offers already in motion are the SI 2 capacity for drawings by Day 60.

Physical clocks: Factory 0 occupy Day 1; 0.0 cells immediately; bathroom 0.1 as Resia comes up; Cloud prototypes in fabrication Day 90; industrial panels in test Day 90; Schweitzer and Unbrick permitted and preparing for production start Day 180; four Cloud prototypes complete Day 180; industrial demonstration product on our site Day 180. Crew arrives before that hardware, not after.

Head of Industrialization and Director of Process Development is one seat right now, not two managers. It reports to Beyreuther to focus on process (SI 3: cells, equipment, Factory 0 layout) and acts as interim Director of Manufacturing Operations through prototyping and process-cell development. This person learns and builds the systems of record the next hire will own. This specialist Director of Manufacturing Operations is hired later, when there is manufacturing operations beyond proto and cells.

Fewer managers, more doers. Do not hire a Manufacturing Operations specialist for this window.

Full MOD assembly 1.0, CLT component factory 0.1, and LAM depot 0.0 benches, replica factories, and depots are mature-state. Not this period.

In seat

Already running. Not hires.

P&L / offtake / strategy

Head of Build

Justin Stewart

Full P&L. Market and offtake development, strategic finance for Build offtake, external development projects, overall strategy.

SI 1 / SI 2 / SI 3 architect

Head of Platform

Todd Beyreuther, PE

Overall owner and architect of the system. The engineer who enables the entire system to work together. Head of Industrialization reports here to begin with.

Ledger / scientific innovation

Head of Ledger

Geoff Staneff, PhD

One ledger from forest floor through flitches, lamstock, CLT, components, assemblies, finished buildings, performance, maintenance, and reconfiguration decades out. Scientific innovation and development of technical innovations for the Platform. Applied material science lives here.

Company

CEO

Justin Dawe

Company leadership.

Offtake

Director of Market Development

In seat, Seattle

New-market introduction and offtake conversion.

Assurance

Director of Digital Backbone

Jennifer Steinhardt, Seattle

Data system under Staneff.

SI 1

Technical Director - product certification

Brent Olsen, PhD

Product certification path alongside Beyreuther’s package.

Staffing

Recruiting - build

Contract, FL

Hiring machine for every wave below.

Market

Public Relations - build

Contract, Oakland

Already on the org chart; not a 6-month search.

SI 1

Lab partners

WSU; OSU (Pease); UO (Fretz); CU (Srubar); others as required

Coupons and assemblies until the Earth Force lab exists.

Day 1 - open / offer / contract

SI 1–3 and Factory 0 occupy start now. These people must be in motion before Day 30.

SI 2

Product Engineer - systems

Offer (contract Seattle, PE/SE)

All product design starts now. Drawings by Day 60.

SI 2

Product Architect - systems

Offer (contract Spokane, AIA)

Configurable boundaries v0 by Day 60.

SI 3 / Factory 0, under Beyreuther

Head of Industrialization

Search reopened, FTE Spokane. Reports to Beyreuther to begin with.

Director of Process Development immediately: Factory 0 cells, equipment packages, Resia integration. Acting interim Director of Manufacturing Operations through proto and cell development, building the systems of record. Reports to the system architect. Needed before fabrication, not after. Not a second executive layer.

SI 3 / Factory 0

Process Engineer

Interim, Spokane

0.0 cells and Resia on Day 1 equipment.

SI 2

Product Engineer - assemblies / Product Designer — assemblies

Contract + FTE Spokane

Cloud prototype set and wet-room / kitchen modules.

SI 1

Codes and Standards / Certifications - build

FTE or contract under Beyreuther

Agency file, listings, and code reports on the Day 1 worklist.

Factory 0

Factory 0 HSE coverage

Contract or assigned lead

Building cannot be occupied for cell development without it.

SI 3 / modules

Additive Manufacturing Engineer

Mathew Pearson, contract WI

Bathroom / kitchen cells, 0.0 toward 0.1.

Build / Stewart

Strategic Projects Senior Associate

Search Day 1. Reports to Stewart. Investment banking / private equity background.

Extends Stewart across finance, operations, and product. Drives initiatives from analysis through execution so they do not queue on the P&L seat.

Finance

CFO

Search opens Day 1. Build functions report to Stewart.

Offtake-finance facilities, working capital, draws, reporting. Stewart keeps strategic finance for Build offtake and institutional counterparties. Shortlist/offer Day 90; in seat by Day 180.

SI 1

Lab and partner POs

WSU and specialty labs

Slots open Day 1; first coupons Day 60.

In by Day 60

Drawings issued. Factory 0 layout and 0.0 cells live. First coupons at lab.

Factory 0 / Cloud

Project Manager - factory development

Interim available (Everett)

Four prototype units into fabrication next.

SI 2 / permit

Project Architect and PE - structural / fire

Contract Spokane / Seattle

Schweitzer and Unbrick permit packages.

SI 2 / Cloud Connect

Project Engineer - MEP

Contract (McCready)

Cloud Connect and wet-room interfaces.

SI 3

Automation / Controls Engineer

FTE Spokane

Cell commissioning as 0.0 stands up.

Finance

Controller

Day 60 seat. Reports to Stewart until the CFO sits.

Draws, close, and reporting from Day 1 spend as Factory 0 cells stand up.

Factory 0

Factory 0 technician crew

Small cell-development crew, not the MOD 1.0 bench

First articles and 0.0 operation. Full production org is later.

In by Day 90

Cloud prototypes in fabrication. Industrial panels in test. Hardware in the shop.

SI 1 / Factory 0

Quality presence for first articles

Assigned under Staneff; not a full QA-manager bench

Conforming first articles while cells are still 0.0 / 0.1.

Finance

CFO shortlist or offer

Search from Day 1

Financing structure memo this horizon.

SI 1 / Industrial

Industrial test support

Knife River + lab slots already open

Panels in test at Newman Lake or WSU.

In by Day 180

Schweitzer and Unbrick preparing for production start and site delivery. Four Cloud prototypes complete and stacked. Industrial demo on our site. First cells defined. Head of Industrialization still acting over Manufacturing Operations - this is still proto and cell development, not a manufacturing-operations specialist hire.

SI 3 / Factory 0

Head of Industrialization (acting Manufacturing Operations)

Same seat hired in Wave 1 — still acting, not replaced

Continues Process Development and acting Manufacturing Operations. Systems of record are being learned and built on live proto and cell work. Do not hire a specialist Manufacturing Operations lead this period.

Site pilots

Director of Site Operations

Stewart is interim; seat TBD WA/CA

Avalanche, townhomes, and Unbrick permitted and delivered on site.

Customers

Offtake conversion

Stewart + Director of Market Development (in seat)

Institutional offtake is Stewart’s work. Conversion mechanics stay with Market Development. No offtake PM layer this period.

SI 3

Founding Ops Manager and Quality Lead - Factory 0

First production-team seats, not the full 1.0 bench

Cells released to production teams. Do not staff MOD 1.0, CLT 0.1, or LAM 0.0 as complete orgs this period.

Finance

CFO

In seat

Offtake and working-capital structures ready to attach to certified capacity.

Not this period

Mature production state. After Factory 1 is at production speed and offtake warrants it.

Mature

Director of Manufacturing Operations (specialist)

Hire later, when manufacturing operations exist beyond proto and cells

Not this period. Head of Industrialization holds the acting seat until then. The org-chart Q1 2027 / Daniel Todd line is this future specialist, not a Day 1 or Day 180 hire.

Mature

MOD assembly 1.0 full bench

Ops, Quality, HSE, Inventory, Logistics - EF Spokane

Production line, not cell development.

Mature

CLT component factory 0.1 full bench

Including lamstock graders, additive / subtractive leads

Component factory at production speed.

Mature

LAM depot 0.0 full bench

TBD

Depot operations.

Mature

Replica factories and depots

MOD (i) × 10+, CLT (i) × 2, LAM (i) × 10

In-market assembly and replica capacity follow Factory 1.

Mature

Data / QA manager benches

IoT, data systems, ledger, QA, environmental, safety managers

Staneff holds process of record now. Benches come with production scale.

Mature

Estimating, scheduling, procurement specialization

Future offtake operations

After offtake is converting at volume.

Mature

Earth Force lab operations staff

After lab is built

Lab is designed this period, not operated.

Mature

Director of Product Development

Not this period

Beyreuther is the authority. Product engineer and architect are the doers. A product-development director now is a manager beside the best person in the niche.

Mature

Director of Policy Development / Director of Content Development

Not this period

Permit PE/architect and Market Development are the doers. Director seats wait for scale.

Mature

Offtake project-management layer

Not this period unless conversion volume requires it

Stewart and Market Development hold offtake. Do not add a PM layer on top of the people who already do this.

09

First 30 days

  1. A1

    Factory 0 occupied and usable for cell development.

    StewartBuilding in use

  2. A2

    Resia commissioned equipment acquired. Bathroom / kitchen module cells started. Beyreuther is the architect; Stewart holds commercial control. Head of Industrialization takes cell development when seated, reporting to Beyreuther.

    Beyreuther / Stewart, then IndustrializationEquipment under EF control

  3. A3

    Certification and approved-agency file opened. Lab and partner POs placed. Certification package on the SI 1 worklist.

    BeyreutherFile and POs live

  4. A4

    Supplier POs and deposits issued for the 18-month hardware clock (IFG, Mercer International, KLH).

    Beyreuther / StewartPOs out

  5. A5

    Initial scopes locked: Schweitzer Avalanche and townhomes; Unbrick; four Cloud factory prototypes; industrial panels/assemblies at Newman Lake.

    StewartSigned scopes

  6. A6

    Ledger live: forest floor through flitches, lamstock, CLT, components, assemblies, and first Factory 0 cell cycles. First coupon and first cell write to it. Templates without a write are not done.

    StaneffLedger live; first writes

  7. A7

    CFO search open. Strategic Projects Senior Associate search open (reports to Stewart; IB/PE). Product engineer and product architect offers under Beyreuther. Head of Industrialization search reopened, reporting to Beyreuther to begin with (Process Development immediately; acting Manufacturing Operations through proto and cells). No Director of Product Development, Policy, or Content this period.

    Stewart / Beyreuther / StaneffSearch / offers live

  8. A8

    Factory 1 site-selection file and build-to-suit path with ATI / Leavitt Capital / Aaron Lake.

    StewartMemo v1

  9. A9

    Offtake structures and working-capital facility map opened.

    StewartWorkplan v1

  10. A10

    WSU and specialty-lab slots opened and test matrix includes mill variance (IFG, Mercer, KLH). Earth Force lab design started (Beyreuther). Knife River co-engineering started (Stewart commercial, Beyreuther technical).

    Beyreuther / StewartKickoff and slots

10

Day 60 / 90 / 180

Customers and finance

Stewart, CFO

Day 60

Schweitzer Avalanche, townhome, and Unbrick packages in production design. Cloud prototype drawings released. Industrial drawings with Knife River. Offtake-finance outline. Working-capital map.

Done when: Drawings issued; finance outline circulated

Day 90

Cloud prototypes in fabrication at Factory 0. Industrial panels in test at Newman Lake or WSU. Financing structure memo. CFO shortlist or offer. Conversion plan tied to diffusion studies.

Done when: Hardware in shop or lab; memo; CFO status

Day 180

Schweitzer and Unbrick preparing for production start, permitted for site delivery. Four Cloud factory prototypes complete or in factory. Industrial demonstration product on our site in motion. Offtake and working-capital structures ready to attach to certified capacity. Cypress / LH Housing remains offtake conversion.

Done when: Permit and production status; four Cloud units; industrial demo status; finance package

SI 1 — Characterized and certifiable platform

Beyreuther

Day 60

Test matrix issued, including incoming mill variance (IFG, Mercer, KLH). First coupons and assemblies at WSU or specialty labs, each written to the ledger. Agency pre-application scheduled.

Done when: Matrix, lab log with ledger writes, meeting date

Day 90

Major technical risks listed with owner and test. Certification strategy v1 (agencies, listings, code reports).

Done when: Risk register; cert plan v1

Day 180

Characterized basis sufficient to commission first cells. Component-set rules issued so later factories copy them. Earth Force lab design ready to bid.

Done when: SI 1 package

SI 2 — Designed and documented build system

Beyreuther (doers: product engineer, product architect)

Day 60

Shared-component list v0 is the primary artifact. Product set is the configurations of that list. Wet-room / kitchen modules and Cloud Connect on the list. No product-specific part outside the set.

Done when: Component list v0; products mapped to it

Day 90

Component list v1 and reuse matrix. Permit strategy for Schweitzer and Unbrick as configurations of the set. A part not on the list does not proceed toward 6-month production start.

Done when: List v1; reuse matrix; permit path; out-of-set parts killed

Day 180

Design-to-cost, scope, schedule, and performance sheets sufficient to price and permit Schweitzer and Unbrick as configurations of the set. Cloud four-unit factory set documented on the same list. Industrial panel/assembly package documented with Knife River. Unnecessary parts designed out.

Done when: SI 2 package = set + configurations, not five systems

SI 3 — Designed and documented production system

Beyreuther (architect); Industrialization when seated. Stewart: P&L, capex, Factory 1.

Day 60

Factory 0 layout and cell list v1. Each listed cell has a copy-package outline (equipment, utilities, quality limits, labor, ledger points). Resia integration in process. Bathroom / kitchen module cells at 0.0 with path to 0.1. Supply map: IFG, Mercer International, KLH.

Done when: Layout, cell list with copy-package outline, supply map

Day 90

Equipment packages and utility interfaces for first cells. Factory 0 safety and commissioning criteria. First-article criteria on the ledger. Factory 1 build-to-suit memo updated.

Done when: Equipment book; safety draft; ledger first-article fields; BTS memo

Day 180

Production-system package ready for Factory 1 discussions. First cells defined as copy-packages and released. In-market assembly not in this period.

Done when: SI 3 package = cells that can be copied

Hiring sequence

Stewart, Recruiting — build

Day 60

Product engineer and architect seated or contracted under Beyreuther. These are doers, not a Product Development director yet. Head of Industrialization search in late stage, reporting to Beyreuther (Process Development + acting Manufacturing Operations). Process engineer and Factory 0 HSE in. Lab POs live. Strategic Projects Senior Associate in seat or late-stage under Stewart. Controller in seat (reports to Stewart until CFO sits). CFO search active (reports to Stewart). Small cell-development crew identified.

Done when: Doers in place under the three principals; no extra director layer

Day 90

Factory PM and prototype crew on the floor for Cloud fabrication. Quality presence under Staneff for first articles. CFO shortlist or offer. Permit PE/architect engaged as doers for Schweitzer and Unbrick — not a Policy director.

Done when: Crew in shop before hardware; CFO status; permit doers named

Day 180

Head of Industrialization still acting Manufacturing Operations — no specialist Mfg Ops hire. Site Operations seat named for Schweitzer/Unbrick delivery. Founding Factory 0 production seats as cells are released. CFO in seat. Offtake stays with Stewart and Market Development; no PM layer unless conversion volume requires it.

Done when: Acting Mfg Ops still industrialization; site seats named; CFO seated; no extra directors

11

Scope of this period

In scope

Factory 0 cell development as copy-packages; Resia Day-1 equipment; SI 1–3 on one certified set; Schweitzer and Unbrick design, engineering, permitting, and preparation for production start at six months as configurations of the set; four Cloud factory prototypes; Knife River industrial panels, assemblies, and demonstration product; ledger from first coupon and first cell; lab design; Factory 1 site selection and planned build-to-suit; offtake and working-capital structure; Strategic Projects Senior Associate under Stewart; Controller at Day 60; CFO hire; Head of Industrialization as Process Development and acting Manufacturing Operations; doers under Beyreuther and Staneff.

Not this period

In-market assembly facilities; Factory 1 construction; Cloud or industrial customer-site production; Earth Force lab operations; full MOD / CLT / LAM production benches and replica factories; specialist Director of Manufacturing Operations; Director of Product Development, Director of Policy Development, Director of Content Development; offtake PM layer; any product-specific part outside the certified set.

12

Work product

The brief is the story. These are the files, contracts, drawings, tests, and systems underneath it. Paste a Drive, SharePoint, Dropbox, or lab URL when the live document exists — the card stays even while the URL is empty.

5 of 20 linked

Company

Memo

Operating Plan — First 6 Months (Word)

Designed Word brief of the living plan. Includes Controller at Day 60 and Strategic Projects Senior Associate under Stewart. Budget stays in the controlling document.

On this brief

System of record

Staneff ledger — forest floor through decades of building performance

One ledger. Live from first coupon and first cell. Scientific and technical innovation on the Platform.

URL not linked yet

Memo

EF Build — 6 months deck

Working deck this brief was written from. Story stays here; numbers stay in the budget.

On this brief

SI 1 — Platform

Lab / test

WSU and specialty labs — test slots

Coupons and assemblies until the Earth Force lab exists. OSU, UO, CU as required.

URL not linked yet

Certification

Beyreuther certification package

Code reports, product / process / environmental certs, chain of custody, QA/QC, factory certification.

URL not linked yet

SI 2 — Build system

Drawing / package

Shared-component list v0

Primary SI 2 artifact. Products are configurations of this list. Empty URL until the file exists.

URL not linked yet

SI 3 — Production system

Supply

Resia Manufacturing — commissioned bathroom / kitchen equipment

Acquired Day 1. Module cells 0.0 toward 0.1. Specified to be copied.

URL not linked yet

Avalanche SFH

Contract / LOI

Schweitzer Mountain — executed LOI (Avalanche, townhomes, stacked flats)

High-end configurable product that teaches the set. Site pilots.

URL not linked yet

Unbrick

Contract / LOI

Unbrick USA — executed LOI, 500+ units/year path

Product SFD offtake. Production start at six months only for parts in the certified set.

URL not linked yet

Cloud stacked flats

Contract / LOI

Cloud Apartments — Cypress Equity / LH Housing offtake path

Four Factory 0 prototypes this period. Stacked-unit offtake path.

URL not linked yet

Industrial / Knife River

Contract / LOI

Knife River Precast — industrial building system co-engineering

Newman Lake. Test panels, assemblies, demonstration on our site. Factory 1 building system.

URL not linked yet

Factory 0

Place

Factory 0 — 11016 E Montgomery Dr, Spokane Valley

77,000 sq ft, former Katerra Factory 0. Process-cell development, not a production line.

URL not linked yet

Factory 1

Place

Factory 1 — ATI / Leavitt Capital / Aaron Lake build-to-suit

Site selection. Purpose-built production factory using the EF / Knife River industrial system. Planning, not closed.

URL not linked yet

Fiber and panels

Supply

KLH — international CLT panels and components

Import bridge. Characterized alongside Mercer and IFG so the set is not mill-specific.

URL not linked yet

Supply

Mercer International — CLT panels

Immediate panels. Bridge while U.S. conversion comes online.

URL not linked yet

Supply

IFG — domestic fiber

Immediate fiber. SI 1 test matrix includes mill variance.

URL not linked yet

Hiring

Memo

EF Build people 2026

Org and hiring sequence source. Stewart → Beyreuther → Staneff, then doers.

On this brief

Customers and finance

Finance

Vision Ridge Partners — $250M investment stake

Controlling investment. Term sheet May 2026. This brief is the operating plan that budget funds.

URL not linked yet

Finance

Controlling 6-month budget

Spend lives here — not in this brief. The brief is the operating plan that this budget funds. Not an Ask.